War and Delay Claims, Notice, and Records: What to Keep in Mind.

21 May 2026

Giuseppe Broccoli

Written by Giuseppe Broccoli

2 MIN READ

The recent war in Middle East and the consequent closure of the Strait of Hormuz are causing substantial issues to the international commerce. When a project is affected by conflict, sanctions, shipping problems, or supply-chain disruption, the immediate issue is usually delay. The hidden issue is documentation. In construction industry and international commerce, delay claims often succeed or fail depending on what the affected party did in the first days and weeks after the event.

Force majeure

Whether the delay can trigger force majeure or the hardship, there are certain common actions that the affected party has to take with no delay.

The first priority is notice. Most sophisticated contracts require the affected party to notify the other side within a specific period and in a specific form. The notice usually needs to identify the event, explain the impact on performance, and reserve rights under the contract. A late or vague notice can significantly weaken the position of the party seeking relief.

The second priority is records. Parties should preserve the evidence that shows how the event affected the project. This may include correspondence with suppliers, shipping documentation, customs records, procurement attempts, subcontractor communications, site reports, and internal assessments of delay impact. The more complex the project, the more important it becomes to build a clear factual timeline.

This approach is good contract management not just good litigation practice. Even where Saudi law or the contract may ultimately support relief, a claim will be difficult to prove if the factual record is incomplete. The legal analysis depends on causation, and causation depends on evidence. A business that acts quickly and methodically is in a stronger position than one that tries to reconstruct the story months later.

In construction contracts, this issue is especially sensitive because delay often affects several contractual mechanisms at once: extension of time, cost claims, suspension rights, and possibly termination thresholds. The party must therefore understand not only the substantive legal basis for relief, but also the procedural steps required to preserve it. Under FIDIC-type arrangements and similar project forms, that procedural discipline is often decisive.

Saudi law adds another layer of importance because the substantive theory of relief may differ from what common law provides. A party may be able to argue impossibility or excessive burden, but it still needs a clear factual and contractual framework to support the claim. 

In disruption cases, the strongest claims are usually the best documented ones. Prompt notice, careful records, and a disciplined chronology are often worth more than general statements about the seriousness of the conflict. 

 

OTHER POSTS YOU MIGHT BE INTERESTED IN

 

 

 

join our Community